The data file to import Condition Assessments must consist of nine (9) comma separated columns. The columns must be in the following order:
Column |
Field |
Required/Optional |
Description |
1 |
Assessment Date |
Optional |
If no date is supplied, this will be defaulted to the date of import. |
2 |
Current Rating Code |
Required |
The value in this field will be added to the Ratings table if it does not already exist. |
3 |
Priority Description |
Required |
The value in this field will be added to the Priority table if it does not already exist. |
4 |
Comments |
Optional |
This is the condition assessment comments. |
5 |
Asset Number |
Optional |
The assessment must contain either an asset number or a location code. |
6 |
Location Code |
Optional |
The assessment must contain either a location code or an asset number. |
7 |
Work Element |
Optional |
The value in this field will be added to the Work Element table if it does not already exist. |
8 |
Work Element Priority |
Optional |
The value in this field will be added to the Priority table if it does not already exist. |
9 |
Advance/Delay |
Optional |
The value for the Advance/Delay field must be in the following format: <A/D> <n> <X>. The first character must be "A" to indicate an Advance, or "D" to indicate a delay. <n> is the number of days, weeks, months or years that you want to advance or delay by. <X> is the advance/delay units, either "D" for days, "W" for weeks, "M" for months, or "Y" for years. For example, a delay of 4 weeks would be: D 4 W |