Schedule Report

The Schedule Report lists the details of schedules defined in the system. The schedules will only be printed on the report if they have at least one MWA attached to them. You can also choose whether to print the information about the MWAs that are attached to the schedule.

Report Parameters:

To run the Schedule Report:

  1. Run the Schedule Module.

  2. Choose Schedule from the Reports menu option.

  3. Choose whether to include information about the attached work orders. Click the OK button.

  4. Select the parameters for the report (if any). Click the OK button on the report parameter window to run the report.